The following criteria was used to provide this conceptual
budget estimate:
I . Concept drawings SK-1 and SK-2 dated 5 September
1996 were used as the basis of the conceptual budget estimate.
The purpose of this abbreviated study phase is to not develop
a final Schematic Design but to establish a reasonable budget
for the project based on a reasonable diagram.
2. Monies were not included in this estimate for
fixtures, furniture and equipment.
1. SITEWORK
$197,000
The sitework includes the demolition of 15 existing
parking spaces at the south side of the building, 18 new parking
spaces at the north side of the building, re-striping of the existing
northern parking lot (across the road from the library) for 13
new parking spaces, lowering an existing underground electrical
line at the vicinity of the great room, installation of brick
pavers for walkways and the plaza, and a installation of a handicap
access ramp. A. Eliminate brick pavers at west side of building (44,000) B. Substitute concrete sidewalks for 80% of brick pavers at plaza (20,000)
C. Eliminate 18 new parking spaces at employee entrance
(8,000)
Sitework (if deducts A through C accepted)
$125,000
11. RENOVATIONS TO EXISTING BUILDING (27,880 SF)
$760,000
The renovations include demolition of existing walls
and installation of new structure required for roof and new wall
openings, new gypsum board finished interior partitions, new carpet,
new 2x4 lay-in ceiling tiles, two new HVAC units, new ductwork,
relocation of various equipment from the existing courtyard (township
to relocate two HVAC units to Health Department roof), new light
fixtures, new fire shutters at existing windows at Health Department
wall adjacent to library addition, and a new kitchenette at the
new staff room. A. Eliminate new floor finishes at technical services (5,000) Renovations To Existing Building (If deduct A accepted) $755,000
III. NEW CONSTRUCTION (18,000 SF)
$2,100,000
New one story construction includes concrete slab
and steel structure, exterior brick and concrete block cavity
walls with metal and built-up roofs, aluminum/glass walls, aluminum
entrance doors, interior gypsum board partitions, wood interior
doors, carpeting, pavers at the entranceway, 2x2 lay-in ceiling
tiles and a gypsum board ceiling at the great room, vinyl wall
base, 2x2 fluorescent lights and incandescent high hat lights
at gypsum board ceilings, fire alarm system for the entire building,
sprinkler system for the entire building,, and a movable partition
and a projection screen at the meeting room. A. Reduce height of new construction to 15'/21' (170,000) B. Substitute metal stud for masonry backup construction at new entry (10,000) C. Substitute dryvit type wall finish for brick at great room exterior walls (10,000) D. Substitute asphalt shingles for metal roofing at gable roofs (30,000) E. Leave structure exposed at great hall in lieu of gypsum board ceilings (36,000) F. Substitute brick and metal stud walls for aluminum/glass walls (34,000) G. Substitute carpet for ceramic tile pavers at the friends area (10,000) H. Eliminate the arcade and covered entrance (125,000)
1. Eliminate the plaza at the entrance (25,000)
New Construction (If deducts A through I are accepted)
$1,650,000
IV. NEW CONSTRUCTION - HEALTH DEPARTMENT (400 SF)
$45,000
New one story addition that includes a waiting room
for twelve and an entrance foyer. Materials to match those materials
already described for the new construction at Section 111. V. SUMMARY CONSTRUCTION $3,102,000 CONTINGENCY (5 %) 155,000
CONSULTANT FEES (10%) 325,000 CONCEPTUAL BUDGET ESTIMATE $3,582,000 Conceptual Estimate Budget If All Deducts Are Accepted $2,970,000
WYD090596.costest
|